(A) resource assignment
(B) resource leveling
(C) resource splitting
(D) resource scheduling
Category: Project Management Mcqs
Which from the following represents the correct project cycle?
(A) Planning→Initiating→Executing→Closing
(B) Planning→Executing→Initiating→Closing
(C) Initiating→Planning→Executing→Closing
(D) Initiating→Executing→Planning→Closing
Which from the following is NOT an intangible element?
(A) Utility
(B) Public benefit
(C) Brand recognition
(D) Good will
Which from the following is NOT a tangible element?
(A) Fixtures
(B) Trademarks
(C) Monetary assets
(D) Stockholder equity
Business Value =
(A) Tangible Elements
(B) Intangible Elements
(C) Tangible Elements – Intangible Elements
(D) Tangible Elements + Intangible Elements
If any one factor of a project changes, _____ other factor is likely to be affected.
(A) all
(B) one
(C) at least one
(D) at most one
Projects management is divided in _____ process groups.
(A) 5
(B) 7
(C) 9
(D) 11
Which from the following statement(s) is/are NOT true?
I. Projects have defined objectives
II. Programs have a larger scope than projects
III. The projects and programs in a portfolio must be directly related
(A) I only
(B) II only
(C) III only
(D) II and III only
A program is usually a group of
(A) plans
(B) people and work
(C) related projects
(D) unrelated projects
A process that involves continuously improving and detailing a plan as more detail become available is termed as
(A) project analysis
(B) project enhancing
(C) progressive deliberation
(D) progressive elaboration